Sycamore Grove Park has been a public park since 1905. In those 121 years, the city has never written it a master plan. That changed on September 17, 2026, when the Board of Recreation and Park Commissioners approved a $990,000 contract with Stayner Architects to write one for the park and for Ramona Hall Community Center. According to the board report, the city is doing this now because the park's infrastructure and amenities are "reaching the end of their lifespans."
The city is working on the park along two separate tracks. A smaller accessibility project, approved in March, already covers the walkways, ramps and restrooms. The master plan covers what that project leaves out: the bandshell, the trail to the river, the tennis courts, Ramona Hall, and the North Branch of the Arroyo Seco, which runs underground. Those are the parts of the park still open to public input.
The fixes that are already funded
On March 5, 2026, the commission voted 4–0, on its consent calendar, to approve the Sycamore Grove Park Path of Travel Improvements. The budget is $1,127,040.96, paid entirely from Park Fees collected within five miles of the park. Board Report 26-049 splits the work into two phases.
Phase 1, billed in the report as "90 Day Improvements":
- Repave every walkway with compliant asphalt
- Add asphalt paths to the picnic areas and replace the tables there with accessible ones
- Replace the playground handrails where the curved ramps, extensions and heights fall short
- Rebuild the concrete ramp to the existing restroom
Phase 2, the longer-term work:
- Remodel the existing restroom
- Demolish the adjacent concessions building and replace it with a compliant restroom, once its historic status is confirmed
The concessions building is a contributing element to the Highland Park–Garvanza Historic Preservation Overlay Zone. The report says any repairs will follow the Secretary of the Interior's standards for historic properties. The city's schedule had Phase 1 construction in February and March 2026. Phase 2 construction is scheduled to run through September 2027, with post-construction work running to January 2028. The report also states that the project "will have no impact on the existing trees and shade."
That project covers getting around the park and the restrooms. The master plan starts from there.
What the plan inherits
The city describes Sycamore Grove as about 16 acres along the Arroyo Seco and one of the oldest parks in Los Angeles. It sits close to the Charles Lummis "El Alisal" Home, Montecito Heights Recreation Center, Ernest E. Debs Regional Park, Arroyo Seco Park and Heritage Square. Its current park listing names four features: barbecue pits, a children's play area, picnic tables and lighted tennis courts.
The best-known structure is the Sousa-Hiner Bandshell. The Angels Walk LA Highland Park guidebook dates the bandstand to the 1920s and says its Spanish Colonial design was remodeled into its present form around 1950. PBS SoCal reported that the stage was renamed in 2005 for the friendship between John Philip Sousa and Dr. Edwin M. Hiner. Sousa's band played in the park, and Hiner lived across the street, in a house that became a city Historic-Cultural Landmark in 1972.
Ramona Hall is a historic community hall and ballroom that the master plan covers alongside the park. The city's Ramona Hall page lists dance, martial arts, cheer, music, after-school and preschool programs, and camps. The building has an auditorium, a ballroom, a stage, a banquet hall, a kitchen and meeting space.
In The Eastsider's coverage of the city's request for proposals, Jamie Tijerina, president of the Highland Park Heritage Trust, described what the park means locally:
"Sycamore Park holds a lot of memories for our community. It is a gathering place for family milestones like children's birthday parties and community events like tree giveaways and musical performances."
The Eastsider also reported that she named two places needing work. She said the trail to the river could be far more educational, and that the bandshell area could use built-in, up-to-date entertainment infrastructure. According to the same article, the city's request listed the tennis courts, the bandshell, the playgrounds and the fitness zone as areas of interest. It also listed the North Branch of the Arroyo Seco, which has run underground in a channel since around the 1930s.
None of those items is part of the March project. All of them are within the master plan's scope.
The team drawing it
Stayner Architects leads the work. Christian Stayner is the prime project manager, and Jackie Hensy is the lead project manager. Hensy managed the Climate Resilience Environmental Education Center vision and master plan for the Annex and Oak Woodlands at Hahamongna Watershed Park. The board report says Stayner designed that center around the alluvial scrub habitat of the Arroyo Seco.
The rest of the team is listed below.
- McMillen leads the environmental assessment. The board report credits the firm with more than 20 years of river and stream restoration, connectivity and public-access work in the Arroyo Seco and Los Angeles River watersheds.
- Collective UNbound, led by Christopher Locke, coordinates community engagement. Locke sits on the board of CicLAvia.
- Subconsultants include Agency Landscape + Planning, Terremoto, Test Plot, Miasto, Elizabeth Brennan Strategies, Westside Acoustics and Rlatta Consulting.
Test Plot is the native-planting group whose garden sits at the end of the new trail on Elephant Hill in El Sereno.
The board report also says outreach will cover "preservation of cherished park features, opportunities for improvement, and the potential for exciting new elements and connections." The team plans to use scale models and run a statistically valid survey.
How the year of input is set up
The RFP gives the consultant 24 months from the city's notice to proceed. The draft master plan is due in about the first 12 months. The final plan and a programmatic environmental impact report take the second 12. Here is the process the board report lays out, in order:
- Kickoff. Locke leads a Designing with Justice Workshop to set up the engagement process.
- Outreach and survey. The schedule includes a set number of Steering Committee meetings and phased community outreach, with time allowed for comment periods.
- Draft plan. The draft sets short- and long-term design goals and proposes changes that can be built in phases.
- Final plan. The final plan sets the scope, budget and schedule for each recommended project and names possible funding sources. Environmental clearance for each project is handled as a separate task.
The outreach area extends well past Highland Park. The board report names Mount Washington, Montecito Heights, Garvanza, Hermon, Cypress Park, Monterey Hills, Happy Valley and Rose Hill. It also names Council District 1, local schools, cultural institutions and four neighborhood councils: Arroyo Seco, Historic Highland Park, Hermon and LA32.
The city's project page for Sycamore Grove Park and Ramona Hall currently reads "More information to come!" The city's park listing puts total Measure A funding for the planning effort at $1.1 million.
A park with a 1920s bandshell, a historic ballroom and a concessions building inside a preservation zone will get the most out of its next plan when the people who use it weigh in. If you'd like to talk about the park, the streets around it, or how the Highland Park–Garvanza HPOZ affects older buildings nearby, Maureen Pearson is glad to compare notes. Let's Connect.